Proposition B: Roads and Drainage Improvements

Bond Package:  6 Projects / $11.8 million

Proposition B provides funding to construct much needed roadway repairs and drainage improvements to Eanes Creek/Camp Craft Road, Redbud Trail, Westlake Drive, Laurel Valley Road, Yaupon Valley Road, and Terrace Mountain Drive.

The bonds team has been diligently preparing for the roadway and drainage improvement projects. Each project undergoes a thorough process that involves finalizing project designs, working with property owners to obtain necessary easements, and obtaining permits before construction can begin. 

The City will bid out the projects on Eanes Creek/Camp Craft Road, Westlake Drive, Yaupon Valley Road, and Redbud Trail to expedite improvements. Other projects will move forward at later dates as easements and permits are collected. 

Roadway Design Updates: 

  • Summer 2023:  Construction documents have been completed and the design team is working on obtaining permits from state and local agencies, including the TCEQ.
  • Ongoing:  Working with property owners to obtain necessary easements.

Once easements are obtained for the projects, the City will bid the projects. Construction could begin in 2024 and start dates for each roadway project are dependent on the permitting and easement process.

Updates will be shared as new information becomes available.

Eanes Creek / Camp Craft Road  

Project Description:  Replacement of Eanes Creek crossings at Camp Craft Road and Eanes School Road with improved culverts; raise Camp Craft Road by about 6' and Eanes School Road by about 1.5'.
Anticipated Project Cost:  $2,162,000
Estimated Construction Start:  TBD
Estimated Construction Duration:  6 Months

Redbud Trail   

Project Description:  6,500 feet of drainage ditch improvements, replacement of two culverts, and a retaining wall along the northern ROW to grade the proposed ditch. Also includes obtaining a 25' drainage easement from the proposed cross culvert to Little Bee Creek.
Anticipated Project Cost:  $3,724,525
Estimated Construction Start:  TBD
Estimated Construction Duration:  6 Months

Westlake Drive  

Project Description:  Replacement of Little Bee Creek crossing Westlake Drive with larger culverts; including 645 feet of ditch improvements westward along Laurel Valley Road; 1.335 feet of ditch improvements along Westlake Drive; and 450 feet of ditch improvements along Redbud Trail east and west of Westlake Drive.
Anticipated Project Cost:  $1,909,950
Estimated Construction Start:  TBD
Estimated Construction Duration:  6 Months

Laurel Valley Road 

Project Description:  Replacement of four culvert sites from Westlake Drive west to Yaupon Valley at two intersecting points, Ledgeway and a tributary of Little Bee Creek. Little Bee Creek crosses Laurel Valley at three locations; the tributary to Little Bee Creek crosses at another location. Also involves 840 feet of ditch improvements from Double Fork Road to Ledgeway.
Anticipated Project Cost:  $1,661,825
Estimated Construction Start:  TBD
Estimated Construction Duration:  6 Months

Yaupon Valley Road  

Project Description:  Various drainage ditch improvements on the western end of Yaupon Valley, including culverts and reinforced concrete pipe from Juniper to Madrone Road.
Anticipated Project Cost:  $669,250
Estimated Construction Start:  TBD
Estimated Construction Duration:  4 Months

Terrace Mountain Drive  

Project Description:  Improvements to roadside rights of way from Caravan Circle to Westlake Drive, including drainage ditches and replacing four (4) culverts to efficiently convey flow to Bee Creek. The project also includes roadway reconstruction and repaving from Caravan Circle to Westlake Drive.
Anticipated Project Cost:  $946,275
Estimated Construction Start:  TBD
Estimated Construction Duration:  4 Months

Project Updates:

Send an email with the subject line "Prop B Updates" to sign up to receive updates on the roads and drainage improvement projects.

Contact Us:

Email
(512) 327-3628